15 de junio de 2025

Radio 26 – Matanzas, Cuba

Emisora provincial de Matanzas, Cuba, La Radio de tu Corazón

More than 90 percent of the photovoltaic solar park in Martí is completed (+audio).

This was confirmed by engineer Israel Prado Almendariz, investment director of Matanzas Electric Company.

With mounted inverters, the culmination of the placement of panels and sustained progress in the wiring, which exceeds five kilometers in length, the photovoltaic solar park of this municipality of Matanzas is nearing 90 percent completion.

This was confirmed by engineer Israel Prado Almendariz, investment director of the Matanzas Electric Company. The perimeter lighting and other technical works are also being completed. After the completion of the remaining work objects, they will move on to the commissioning phase, which requires a detailed review of each system and also includes foreign consultancy.

…ONLINE AUDIO

Written by José Miguel Solís.

 

Deja una respuesta

Tu dirección de correo electrónico no será publicada. Los campos obligatorios están marcados con *